Yorke 3 Townhomes – Construction Update

Quick Answer

The construction of the Yorke 3 Townhomes progresses through six defined stages: Approvals, Foundation, Rough-ins, Finishing, Inspection, and finally, Occupancy. This structured process guides the development from start to completion. As of October 31, 2022, Buildings 1-8 of the Yorke 3 Townhomes are completed, while Buildings 9-14 are in the Finishing stage.

Yorke 3 Townhomes – Construction Update

Yorke 3 Townhomes by TRUMAN

What is the location of Yorke 3?

128 Avenue N.E. and Cornerstone Street N.E.

Estimated Completion:

Not earlier than March 31st, 2022 and no later than July 1, 2023

Current Progress:

Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy
Construction Progress Updates - Stage 6

Latest Updates:

Updated October 31, 2022:
• Buildings 1-8 are completed
• Building 9-14 are in Stage 4, Finishing

Updated September 9, 2022:
• Buildings 4-6 are completed
• Building 7 & 8 are in Stage 4, Finishing and almost at occupancy stage
• Buildings 9-14 are in Stage 4, Finishing

Updated August 11, 2022:
• Buildings 4 & 5 are completed and at the Occupancy stage
• Buildings 6–11 are in Stage 4, Finishing
• Buildings 12–14 are in Stage 3, Rough-ins

Updated June 17, 2022:

Updated June 13, 2022:
• Buildings 8-14 are in Stage 3: Rough-ins
• Buildings 4-7 are in Stage 4: Finishing

Updated May 9, 2022:




Updated April 13, 2022:

Updated March 28, 2022:
Buildings 4-10 are at various levels of rough-in, drywall and framing with Buildings 1-3 nearing Finishing stage completion. Buildings 10-14 are completing foundation.

Truman - Live better. Live Truman.

 

Live better.®

Frequently Asked Questions

1 What are the construction stages for the Yorke 3 Townhomes?

The construction of the Yorke 3 Townhomes progresses through six defined stages. These include Approvals, Foundation, Rough-ins, Finishing, Inspection, and finally, Occupancy. This structured process guides the development from start to completion.

2 What is the estimated completion timeframe for the Yorke 3 Townhomes?

The Yorke 3 Townhomes are estimated to be completed no earlier than March 31st, 2022. The latest projected completion date is July 1, 2023. This provides a clear window for when the homes are expected to be ready.

3 Where are the Yorke 3 Townhomes located?

The Yorke 3 Townhomes are situated at the intersection of 128 Avenue N.E. and Cornerstone Street N.E. This location places the development in Calgary's North, offering a new perspective for residents.