Walden Duplex – Construction Update

Walden Duplex – Construction Update

What is the construction location for Walden Duplexes?

Creekside Drive S.E.

What is the estimated completion date for Walden Duplex construction?

Not earlier than January 1, 2024 and not later than December 31, 2024

What is the current construction progress for Walden Duplexes?

Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy
Construction Progress Updates - Stage 4

Latest Updates:

Updated March 16, 2023:

Updated October 31, 2022:
• 553/557/561 Walgrove Blvd SW are in Stage 4, Finishing

Possession scheduled for January 4th, 2022

Updated September 9, 2022:
• 545/549 are in Stage 5, Inspection
•  537/541, 529/533, 521/525 are in Stage 4, Finishing

Updated August 11, 2022:
• 553/557/561 are in Stage 3, Rough-ins
• 545/549, 537/541, 529/533, 521/525 are in Stage 4, Finishing

Updated May 9, 2022:

Updated April 13, 2022:

Truman - Live better. Live Truman.

 

Live better.®

Frequently Asked Questions

1 What is the estimated completion timeline for the Walden Duplex homes?

The estimated completion for the Walden Duplex homes is projected to be no earlier than January 1, 2024, and no later than December 31, 2024. This provides a general timeframe for the project's finalization.

2 What are the different construction stages for the Walden Duplex project?

The construction of the Walden Duplex homes progresses through six defined stages: Approvals, Foundation, Rough-ins, Finishing, Inspection, and Occupancy. These stages outline the entire development process from start to finish.

3 How often are the construction updates for Walden Duplex posted?

The page provides periodic updates on the construction progress. While there isn't a fixed schedule mentioned, previous updates were posted on dates such as March 16, 2023, October 31, 2022, and September 9, 2022.

4 Which Walden Duplex units are currently in the finishing or inspection stages?

Based on the latest updates, units 553/557/561 Walgrove Blvd SW were in Stage 4 (Finishing) as of October 31, 2022. Additionally, units 545/549 Walgrove Blvd SW were in Stage 5 (Inspection) as of September 9, 2022, indicating they are nearing completion.