Rangeview

Location:

202 Avenue S.E. and Mallard Gate S.E.

Estimated Completion:

Not earlier than August 1st, 2022 and not later than July 15, 2023

Current Progress:

Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy

Construction Progress Updates - Stage 6

Latest Updates:

Updated April 28, 2023:

Updated March 16, 2023:

Updated October 31, 2022:

Block 6, Lots 1, 3, 4, 17, 18, 19, 20 – Stage 4: Finishing
Block 6, Lots 2 – Stage 2: Foundation/Framing
Block 6, Lots 9, 10, 11, 12 – Stage 2: Foundation/Framing
Block 6, Lots 17, 18, 19, 20 – Stage 4: Finishing

Block 7, Lot 7 – Stage 2: Foundation
Block 7, Lot 8 – Stage 3: Rough-ins
Block 7, Lot 9 – Stage 2: Foundation
Block 7, Lot 10 – Stage 6: Occupancy

Block 8, Lot 1 – Stage 6 : Occupancy

Updated September 9, 2022:

Block 6, Lots 1-18 – Stage 2 – Foundation
Block 6, Lots 19-20 – Stage 3 – Rough-ins

Block 7, Lots 1-9 – Stage 2 – Foundation
Block 7, Lot 10 & 17 – Stage 3 – Rough-ins

Block 8, Lot 1 – Stage 4 – Finishing

Updated August 11, 2022:

Updated May 9, 2022:

Updated April 7, 2022: