Gallery – Construction Updates
What is the location of the Gallery project?
1005 1st Street S.W.
What is the estimated completion date for the Gallery project?
Jan. 1st 2027, and not later than Dec. 31st, 2027
What is the current progress of the Gallery project?
Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy

Latest Updates:
Gallery has now reached Level 19, where the building’s rooftop amenity space will be located. Exterior windows are installed up to Level 13, and interior walls are being framed on Level 12. Plumbing, electrical, heating, and ventilation work has reached Level 10, while kitchen cabinets and other built-in finishes are being installed on Level 6