Dawson’s Street Towns – Construction Update

Dawson’s Landing Street Towns – Construction Update

Location:

Dawson Way

Estimated Completion:

Not earlier than March 31st, 2022 and no later than July 1, 2023

Current Progress:

Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy
Construction Progress Updates - Stage 5

Latest Updates:

Updated March 16, 2023:

Updated November 30, 2022:

  • Block 16, All Buildings – Stage 4: Framing/Finishing
  • Block 17, All Buildings – Stage 5: Inspection

Updated November 2, 2022:

  • Block 17, Lots 10-34 Buildings 1 – Stage 2: Foundation/Framing
  • Buildings 3, 5, 6, 7, 8 – Stage 3: Rough-ins
  • Block 16, Lots 17-33 – Stage 2/3: Completing Framing, starting Rough-ins
  • Block 20 – Stage 1, Approvals

Updated September 9, 2022:

  • Buildings 1,2 & 4 – Stage 2, Foundation
  • Buildings 3, 5, 6, 7, 8 – Stage 3, Rough-ins
  • Block 16, Lots 17-33 – Stage 2, Foundation
  • Block 20 – Stage 1, Approvals