Lincoln – Construction Update

Lincoln – Construction Updates

Gallery by Truman

Location:

11th Avenue and 2nd Street SW

Estimated Completion:

Jan. 2027, and not later than Jan. 2029

Current Progress:

Stage 1: Approvals
Stage 2: Foundation
Stage 3: Rough-ins
Stage 4: Finishing
Stage 5: Inspection
Stage 6: Occupancy
Construction Progress Updates - Stage 2

Latest Updates:

August 2026

Construction continues below ground at Lincoln. A major section of the first underground parking level on the west side is now complete, along with the supporting walls and columns leading up to the main floor.

On the east side, another section of the underground parkade was poured this month, and crews are now building the walls and columns for the level above. The first section of the main floor is expected to be poured by mid-September, followed by the second section near the end of October.

May 2026

Updated May 2026:

Lincoln Condos

Lincoln Condos

November 2025

Updated November 2025:

Lincoln Condos

Lincoln Condos

October 2025

Updated October 2025:

Lincoln Condos

Lincoln Condos

August 2025

Updated August 2025:

Lincoln Condos

Lincoln Condos

May 2025

Updated May 2025:

Lincoln Condos

Lincoln Condos

March 2025

Updated March 2025:

Lincoln Condos

January 2025

Updated January 2025:

Lincoln Condos

Lincoln Condos

Truman - Live better. Live Truman.

 

Live better.®